Research Article | | Peer-Reviewed

Optimization of Retaining Ditch Height for Gentle Slope Turning in Inclined Coal Seam Open-pit Mines

Received: 28 October 2025     Accepted: 20 December 2025     Published: 27 December 2025
Views:       Downloads:
Abstract

Inclined coal-seam open-pit mines with internal dumping commonly reserve an end-side retaining ditch when turning from horizontal advance to along-strike excavation. Selecting a single fixed ditch level is straightforward but ignores year-to-year variability in stripping volumes and haulage distances, which can inflate the combined transportation and secondary stripping costs. This study proposes a two-stage optimization framework for planning the ditch-height trajectory during the turning period. First, a maximum economic ditch height is derived via an economic-compensation model that balances the revenue from overlying coal recoverable after turning against the added costs of longer haulage and increased external dumping, with cost/revenue streams discounted using a compound-interest formulation. Second, within this upper bound, a total-cost minimization model couples annual stripping transportation costs during turning with the secondary stripping cost after turning. The model enforces annual waste-volume balance among inner dumping, ditch storage, and external dumping, preferred waste-flow directions, bounds on ditch height, and limits on height differences between adjacent years. Haulage distances are calculated from centroid locations of stripping and dumping stages extracted from 3DMine, and the resulting dynamic program is solved using a sequential recursion method. A seven-year case study (2023-2029) outputs an optimized fluctuating ditch scheme with yearly ditch heights of 214.5, 190.5, 206.7, 201.3, 189.6, 181.2, and 166.0 m, reducing the cumulative cost by 148.32 million CNY compared with the conventional constant-level ditch plan. The framework offers a practical decision tool for parameterizing retaining ditches and improving the overall economics of gentle-slope turning in inclined coal-seam open-pit mines.

Published in International Journal of Energy and Environmental Science (Volume 10, Issue 6)
DOI 10.11648/j.ijees.20251006.14
Page(s) 162-173
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2025. Published by Science Publishing Group

Keywords

Open-pit Mine, Inclined Coal Seam, Ditch Height Optimization, Fluctuating Ditch, Optimization Modeling

1. Introduction
In the whole life cycle of open-pit mines, since the mining area is generally large, direct mining of the whole area will cause problems such as poor economics. Therefore, mining mines is often divided into two or several mining areas for staged or partitioned mining . For near-horizontal or gently inclined open-pit coal mines, since the inclination angle of the coal seam does not change much, whether digging along strike or along the horizontal mining of the coal seam if the internal drainage conditions are met, a certain distance between the stope and the inner dump site will be maintained, and follow up synchronously. However, for open-pit mines with inclined or steeply inclined coal seams, it is almost impossible to completely transport the wastes excavated along the extension direction of the coal seam to the inner dump, and compared with longitudinal mining, horizontal mining releases a larger inner drainage space . Therefore, during the transition from horizontal mining to vertical mining, trenches need to be used in open-pit mines with internal drainage to reduce the amount of secondary stripping in the next mining area and increase the mine's economic benefits.
At present, the ditch retention methods in steering mainly include end-side inverted triangular ditch, dump site inverted triangle ditch, end-side horizontal ditch, etc. Among them, the horizontal ditch at the end side is the most commonly used method. This method is bounded by a certain level of the side wall . Below this level, the normal internal drainage mode of internal pressure covering the side wall is still adopted, and the method of non-discharge is adopted above this level to keep the minimum groove width. As shown in Figure 1.
Figure 1. Schematic diagram of the horizontal stay trench of the end gang of the open pit mine with inclined coal seam.
In the process of turning to the retention ditch, the determination of the height of the retention ditch plays a vital role in it. Research by researchers on retaining trenches during diversion in open pit mines has focused on a single retaining trench height. For example, Liu Guangwei . established a mathematical model of the height of the inner discharge pressure gang and repeated peeling, and determined the optimal repeated peeling depth by using the minimum repeated peeling ratio. Zhang Ding . calculated the key parameters of the trench height between the two mining intervals by establishing a mathematical model of the economic trench height of the adjacent mining interval of the open-pit mine. Liu Peng . calculated the upper lag time value of different pressure heights based on the input lag time of the secondary divestiture cost as an independent variable. Ma Li . proposed the semi-pressure gang mode of grooved horizontal grooves, and determined the comprehensive optimization model of the height of the inner row pressure gang and the optimization model of the inner row bypass transfer step distance based on the cost compensation method. V. I. Cheskidov increased the capacity of the inner row and reduced the height of the trench by increasing the high slope ratio of the dumping site.
The determination of the height of the above-mentioned ditch is only considered from the perspective of economic compensation or the optimal amount of secondary stripping and does not comprehensively consider factors such as the time during the steering period, the dynamic changes of the stripped objects, and the transportation distance . Moreover, for inclined seam open pit mines, during the transition period of the mining area, the stripping volume of the mining site is uneven for each year or each phase due to the different coal seam inclination, different coal seam thickness, geological formations, etc., and once the retention trench level is fixed during the steering period, it means that the inner drainage field can accommodate a certain amount of stripping for each year . When the maximum retention level is determined with cost compensation, there is no constraint on the minimum retention level, in this case, if the internal drainage field is discharged at the maximum retention level for each year, and the internal discharge is given priority over the external discharge, the economic benefits are maximized in terms of the minimum amount of secondary stripping after turning, but in terms of the overall service life of the mine during turning Therefore, in this paper, we consider the stripping flow and freight costs during the conversion from horizontal to vertical mining and the secondary stripping costs after the conversion to determine the optimal economic benefits of the mine as a whole to constrain the changes in the height of the retention ditch in each period.
In this paper, we study the change in trenching level during the turnaround of the crosscutting row in a tilted seam open pit mine based on the maximum trenching height level and constrain the change in trenching height from year to year by maximizing the overall economic efficiency. This process not only increases the overall internal drainage space, equalizes the annual drainage volume, and reduces the amount of secondary stripping after turning, but also optimizes the trench height to improve the overall economic efficiency. It also provides considerable guidance for the selection of retention trench level parameters during the subsequent open pit turnaround.
2. Maximum Trench Height Under Cost Compensation Constraint
Taking the open-pit mine with a single huge thick inclined coal seam as an example, the economic cost compensation method is used to analyze the maximum trench level. When the full pressurization of the inner drainage field is changed to partial pressurization, the recovery of the overburdened coal resources in this process is compared with the cost of secondary stripping, the cost of increasing the transport distance of the stripped material, and the cost of increasing the external drainage, so as to determine the maximum level of trenching.
When partial pressurization is carried out, the most significant impacts are: the economic benefits generated by the overburdened coal extracted after leaving the trench turned, the stripping costs of the second stripping after turning, the costs resulting from the change from double-loop transport to single-loop transport above the elevation of the left trench to increase the haul distance of the inner row, and the costs of the increased haul distance of the outer row stripping due to the left trench .
Figure 2. Diagram of the steering of the horizontal stay trench in the end gang of the adjacent mining area of the inclined coal seam open pit mine.
Among them, the secondary stripping amount of the next mining area under the unit advance degree is:
(1)
In the formula:
—The amount of secondary stripping under the height difference of ditch retention per unit advancing degree in adjacent mining areas, m³;
—Height difference between the ditch level and the surface, m;
—Pit bottom depth in the first mining area, m;
—coal seam height difference, m;
— side slope angle of the first mining area;
—The side slope angle of the next mining area.
The volume per unit propulsion degree in the unrejected space is:
(2)
In the formula:
—The amount of waste dumped in the outer dump site increased by leaving ditches under the unit advance degree, m³;
—The west bank slope angle of the first mining area.
The volume of overlying coal mined after steering:
(3)
In the formula:
—side slope angle without secondary stripping;
—Inclination angle of the inclined coal seam.
(1) Under the unit propulsion degree, the economic benefit brought by mining the overlying coal after turning is a positive benefit:
(4)
In the formula:
—The unit price of coal, yuan/t;
—The bulk density of coal, t/m³.
(2) Under the unit propulsion degree, the economic benefit brought by the secondary stripping amount after steering is a negative benefit:
(5)
In the formula:
—Unit secondary stripping cost, yuan/m3.
(3) Under the unit propulsion degree, the economic benefit generated by the double-loop transportation of internal dump wastes above the ditch level is converted into single-loop transportation and the increased internal discharge distance is a negative benefit:
(6)
(7)
In the formula:
—The unit price of truck transportation, yuan/m3·km;
—The volume of the waste discharged from double-loop transportation to single-loop transportation, m3;
—The length of the working line at the bottom of the pit in the first mining area, m;
—The distance length increased by double-loop transportation transformed into single-loop transportation, m.
(4) Under the unit propulsion degree, the unused disposal space of the inner dump site will result in the difference cost caused by transporting part of the stripped material to the outer dump site, which is a negative benefit:
(8)
In the formula:
—The cost of land expropriation for the unit’s outer dump site and the increase in the transportation distance of the outer dump, yuan/m3;
Through the comparative analysis of the cost compensation of the three types of costs, combined with the calculation method of compound interest in economics , the maximum level of ditch retention is determined as follows:
(9)
In the formula:
—Bank annual interest rate, %;
—The service life of mining area turning, a.
Put the above formula into the simplification to get the function expression relation of :
(10)
Through the above formula, this paper constrains the maximum height of the ditch at the end side. When the level of the ditch exceeds this height, the economic benefits brought by the ditch are negative. When the ditch is less than or equal to this part What is produced is a positive economic benefit value. The top view and cross-sectional view of the mining area are shown in Figure 3:
Figure 3. Schematic diagram of maximum ditch height in inclined seam open-pit mine.
3. Ditch Height Under Overall Constraints of Total Cost Minimization
Through the above economic benefit compensation method, this paper determines that the maximum height of the ditch during the diversion of the inclined coal seam open-pit mine is , and the height of the ditch will be further restricted in the following.
During the diversion period, the stripping material produced in the stope every year is divided into three parts, which are transported to the inner dump, the ditch space (the amount of ditch discharge) and the outer dump . Among them, it is assumed that the stripped objects transported to the inner dump every year are fixed, that is, the inner dump is discharged according to the normal elevation every year, while the stripped objects transported to the ditch part and the outer dump every year are dynamic change. From this, the relationship between the total cost and these quantities can be determined: when the height of the ditch becomes smaller, the amount of drainage in the ditch is increasing. For the stripped material, the transportation distance decreases, and the economic benefits increase. The economic benefit is also improved when the displacement is reduced, but for the amount of secondary stripping after steering, the amount of secondary stripping increases and the economic benefit decreases; The displacement is reduced, the transportation distance of some stripped objects is increased, the economic benefit is reduced, the external discharge is increased, the economic benefit is reduced, and the secondary stripping volume after the steering is reduced, the economic benefit becomes larger . Now the objective function is to minimize the sum of transportation costs during the steering period and the secondary stripping costs after the steering, accumulate the costs of each part of each year during this period, and make the annual stripping logistics Change to the flow, so that the overall accumulated total economic benefit value is optimal .
3.1. Establishment of Ditch Height Planning Model
The ditch height planning model during the turning period divides the entire model cycle into several stages according to the year, and gives the horizontal height of the ditch in each stage, so that the mine can be stripped in the entire cycle of model calculation, and the economic benefits of transportation plus the two after the steering The sum of the economic benefits of each stripping is optimal. The engineering position of each stage includes the height of the inner dump and the shape of the slope. The unit cost of production links such as perforation, blasting, and mining basically does not change with the change in the height of the ditch. Therefore, the economic benefits of the dynamic programming model for the horizontal height of the ditch during the diversion period mainly consider the cost caused by the change in the amount of stripped objects transported to different locations and The cost of the secondary stripping amount when mining the next mining area after the diversion is completed.
3.2. Scientific Simplification of the Problem
In reality, the flow direction of the stripped material from the internal drainage period of the inclined coal seam open-pit mine to the transition to the longitudinal mining period is to be able to be discharged inward as much as possible (excluding the level of the ditch), and the remaining stripped material is released in the form of internal drainage heightening or external drainage. In this process, factors such as the tracking distance of the inner row, the highest discharge elevation of the inner and outer dumps, the height of each step, the width of the working flat, and the slope angle of the dump all have an impact on it. Complete description, analysis, and analysis: It is costly and difficult to solve all the problems involved in turning to ditch retention, so it is necessary to further simplify the stripping flow each year. The simplification is as follows: determine the minimum tracking distance between the inner dump and the stope as ; determine that the inner dump will be discharged according to the highest elevation except for the ditch part; Only the centroid position of the stripping and discarding stages is considered in each year. The horizontal and vertical distances were calculated according to the position changes of the center of mass in the stripping stage and the corresponding discarding stage; the slope angle of the inner dump site was determined to be a constant value .
3.3. Ditch Dynamic Adjustment Constraint Range
After the relevant simplification of the above problems, according to the development law of mining stripping and drainage engineering, it is necessary to adjust the dynamic planning of relevant stages .
(1) The height of the ditch should be less than the maximum horizontal ditch height , and in the limit state, no ditch should be left, that is, the height of the ditch should be greater than 0.
(11)
In the formula:
—The height of the ditch for each year, m.
(2) Under ideal conditions, the total amount of waste W in each year should be equal to the loose volume corresponding to the stripped amount W in the stripping stage, and the volume of the total amount of waste is equal to the sum of the volumes of waste in each part:
(12)
In the formula:
—is the loose coefficient, dimensionless;
—is the stripping amount in the year, m3;
—is the amount of discharge in the year, m3;
—Internal displacement per year, m3;
—Exhaust discharge per year, m3;
—is the volume of material corresponding to the height of the ditch in each year, that is, the amount of secondary stripping after turning, m3.
(3) Considering the follow-up open-pit mine reclamation work, stripping, and the working parameters of the dumping equipment, the height difference between the horizontal stages of adjacent ditch retention should not be too large, and should be less than or equal to the internal dump site Maximum height difference between adjacent stages:
(13)
In the formula:
—Height of ditch in the next year, m;
—Maximum height difference between adjacent stages of the internal dump, m.
3.4. Model Building
The mining stripping and discarding in the model solution period are considered year by year, and the stope determines the location of the stripping stage, the centroid of the stripping stage and other data according to the fixed advance rate or production capacity, as the known conditions for the model solution . Taking the minimum sum of the transportation cost in the whole diversion and the secondary stripping cost after the diversion as the optimization goal, the height of the trench retention in different engineering positions of the retention level is solved and the optimal cost in the entire calculation period is obtained.
The objective function of the model needs to consider the calculation method of transportation cost , and the calculation mainly considers the horizontal transportation distance, vertical lifting height, and the volume of waste. Right now:
(14)
In the formula:
—transportation cost in a year, yuan;
—The transport cost of efflux in the year, yuan;
—the horizontal transportation distance between the discarding stage and the corresponding stripping stage in each year, km;
—Height difference between the centroid of the discarding stage and the stripping stage of each year, km.
The height of the ditch is as follows:
(15)
In the formula:
—The transportation cost of stripped objects to the ditch in year , yuan;
The height of the ditch is and the second stripping fee per year after turning:
(16)
In the formula:
—The corresponding secondary stripping fee in the year after the diversion, yuan;
Based on the above simplification and analysis, an optimization model for the ditch height during the diversion period of the inclined coal seam open-pit mine under the condition of internal drainage is established:
(17)
(18)
In the formula:
—total cost of expenses, yuan;
That is, the constraint conditions only include four groups of variables: the amount of ditch discharge , the amount of internal dump , the amount of outer dump , and the height of the ditch , and the conditions for the height of the ditch are known according to the above formula Then, the corresponding amount of ditch discharge can be calculated, and because the height of the internal dump is determined, the annual discharge of the internal dump can be determined. According to the total amount of annual discharge, The discharge volume of the outer dump can be obtained. Therefore, the constraint condition is simplified as an expression of a group of variables of ditch height (ditch discharge amount ).
As for the objective function, on the basis of determining and , the geometry of the ditch area can be determined. With the help of mining software such as 3DMine, the coordinates of the centroid of the rejection stage can be determined by using differential, integral, and interpolation methods. The data such as the center of mass of the stripping stage can be obtained directly through 3DMine software, and the horizontal transportation distance and vertical lifting distance can be further calculated according to the centroid of the stripping stage and the discarding stage, and the entire mine can be obtained according to the calculation method of the transportation cost of the specific mine. The total cost for the model calculation period. The fluctuating ditch model is shown in Figure 4:
Figure 4. Schematic diagram of undulating ditch retention in inclined seam open-pit mine.
4. Case Analysis
An open-pit mine belongs to the inclined coal seam open-pit mine. The main recoverable coal seam is a single thick coal seam Group B coal seam, the coal seam dip angle is 4°~31°, and the average mineable coal seam thickness is 69.43m. At present, mining is carried out from north to south in the first mining area, and the method of horizontal mining and internal row is adopted for advancement, and the stripping adopts the single-bucket truck intermittent process. Due to the large advance stripping, the uppermost flat plate is about 1583m away from the boundary of the mining area, and it will soon face the problem of turning. When determining the turning period of the open-pit mine, it is necessary to reserve the end side ditch in advance to reduce the amount of secondary stripping in the mining after turning to the next mining area. The author optimizes the level of ditch retention based on the direction and flow of the stripping material during the seven-year period from the start of ditch retention in 2023 to the end of ditch retention in 2029 in the open-pit mine .
The working line in the first mining area of the open-pit mine is arranged in a straight line, and the minimum tracking distance between the dump and the stope is maintained year by year. The inner dump is discharged according to the surface elevation. When the disposal space is insufficient, it is transported to the outer dump for disposal. Way. As shown in Figure 5:
Figure 5. The current situation of an open-pit mine in 23 years.
The main parameters of the open-pit mine are as follows:
Table 1. Relevant parameters of the open-pit mine during ditch retention.

Main parameter symbol

Numerical size

Unit

β1

35

°

β1

20

°

β2

35

°

β3

35

°

θ

11

°

m

69.3

m

hf

190.5

m

L

1300

m

Lmin

50

m

Pc

131.26

t/yuan

γ

1.27

t/m3

Pr

8.80

yuan /m3

B

2.00

yuan /m3·km

C

3.50

yuan /m3

Bring the above relevant data into the above formula to calculate the maximum ditch height under the effect of economic compensation.
Figure 6. Maximum trench height under the economic compensation method.
It can be seen from Figure 6 that when the mining depth in the initial mining area is 260m, the maximum trench heights calculated by the cost compensation method are 20m and 180m respectively, does not meet the ditch steering requirements. Therefore, the maximum ditch height is taken as 180m. At this time, the horizontal height of the ditch is 80m. On this basis, the model is used to solve the height of the ditch at each stage of the fluctuation change.
4.1. Model Solution Process
When the parameters and formulas are determined, the sequential recursion method is used to solve the model. The model solution process is shown in Figure 7:
Figure 7. Flowchart of solving the dynamic programming model of ditch height.
4.2. Model Calculation Results
According to the stripping flow direction and flow planning of the stripping plan of the open-pit mine from 2023 to 2029, the annual overall stripping volume, flow direction, and corresponding costs of fluctuating changes in the height of the ditch during this period were planned. The results are shown in Table 2. Table 3 shows:
Table 2. The annual stripping flow direction and flow chart of the fluctuating height of the ditch in the open-pit mine.

Year

Annual stripping volume/10,000 m3

External discharge/10,000 m3

Internal displacement/10,000 m3

Amount of internal drainage ditch/10,000 m3

2023

5463.91

1627.56

718.21

3114.14

2024

3861.5

968.17

679.32

2214.01

2025

4889.41

1143.13

984.94

2761.34

2026

5794.19

2140.59

723.67

2629.93

2027

4936.06

1414.14

1146.21

2375.71

2028

4624.38

1567.24

911.81

2145.33

2029

4531.67

2193.11

768.26

1570.03

Table 3. The annual cost of stripped objects in the fluctuating height of the ditch in the open-pit mine.

Year

Expenses for evacuation/10,000 yuan

Inner row cost/10,000 yuan

Internal drainage ditch cost/10,000 yuan

Second stripping cost/10,000 yuan

Total annual cost/10,000 yuan

Ditch height/m

Total cost/10,000 yuan

2023

20670.012

3231.945

7473.936

27404.432

58780.325

214.5

362836.58

2024

13263.929

2581.416

6642.03

19483.288

41970.663

190.5

2025

15889.507

3447.29

6903.35

24299.792

50539.939

206.7

2026

28255.788

2388.111

5785.846

23143.384

59573.129

201.3

2027

20363.616

3553.251

4988.991

20906.248

49812.106

189.6

2028

24762.392

2553.068

3647.061

18878.904

49841.425

181.2

2029

33993.205

1997.476

2512.048

13816.264

52318.993

166

The annual overall stripping volume flow direction and the corresponding cost planning results of the open-pit mine under the normal ditch level during this period are shown in Table 4 and Table 5:
Table 4. The open-pit mine maintains the normal ditch level annual stripping flow table.

Year

Annual stripping volume/10,000 m3

External discharge/10,000 m3

Internal displacement/10,000 m3

Amount of internal drainage ditch/10,000 m3

2023

5463.91

3171.4

718.21

1570.3

2024

3861.5

1611.88

679.32

1570.3

2025

4889.41

2334.17

984.94

1570.3

2026

5794.19

3200.22

723.67

1570.3

2027

4936.06

2219.55

1146.21

1570.3

2028

4624.38

2142.27

911.81

1570.3

2029

4531.67

2192.84

768.26

1570.3

Table 5. The open-pit mine maintains the normal level of trench retention and annual stripping costs.

Year

Expenses for evacuation/10,000 yuan

Inner row cost/10,000 yuan

Internal drainage ditch cost/10,000 yuan

Second stripping cost/10,000 yuan

Total annual cost/10,000 yuan

Ditch height/m

Total cost/10,000 yuan

2023

40276.78

3231.945

3768.72

13818.64

61096.09

166

377668.50

2024

22082.76

2581.416

4710.9

13818.64

43193.71

2025

32444.96

3447.29

3925.75

13818.64

53636.64

2026

42242.9

2388.111

3454.66

13818.64

61904.32

2027

31961.52

3553.251

3297.63

13818.64

52631.04

2028

33847.87

2553.068

2669.51

13818.64

52889.08

2029

33989.02

1997.476

2512.48

13818.64

52317.62

From the above Table 2, Table 3, Table 4, and Table 5, it can be seen that when the same level of normal ditch height is used as a whole to retain the ditch, the total sum of the stripping flow, flow rate, and secondary stripping costs after the diversion is 377668.50 during the ditch retention period. 10,000 yuan; when using the fluctuating type of trench retention at different levels in each stage, the output trench heights are: 214.5m, 190.5m, 206.7m, 201.3m, 189.6m, 181.2m, 166m, and the total cost is the lowest, and the cumulative sum is 3,628,365,800 yuan. Compared with the traditional way of keeping trenches at the same level, it saves 148.3192 million.
5. Discussion
In this paper, based on the linear programming method commonly used in optimization design, combined with the economic benefit compensation method and the cost minimization method, the height of the ditch during the steering period is studied. With the goal of minimizing the total cost of stripping during the turning period and the total cost of the second stripping after the turning period, the influence of fluctuating ditch retention during the turning period is considered.
According to the production characteristics of open-pit mines, during the transition period of the mining area, the method of slowing the side and leaving the ditch is usually used. Drawing lessons from the concept of compound interest in economics, it is restricted to the maximum height of the trench; combined with the minimum sum of costs in this process, a corresponding model is established to constrain the optimal height of the trench at each stage.
Combined with a specific example, collect relevant important parameters of the mine from 2022 to 2028 during the transition period, and substitute them into the above solution model. Compared with the traditional scheme, the net benefit value has increased by 148.3192 million yuan. The optimization effect is obvious.
The ditch height planning model established in this paper is based on the year as a unit, and the overall optimization of the ditch height within 7 years is carried out, and the overall optimal plan is obtained. At the same time, this paper also has the following deficiencies: (1) only considering the impact of the height of the ditch on the economy, ignoring the impact of the height of the inner row; (2) ignoring the planning of each year. But generally speaking, the method proposed in this paper can improve the efficiency of the enterprise as much as possible during the diversion period and has a positive effect on the formulation of the diversion ditch retention plan for inclined coal seam open-pit mines.
6. Conclusion
(1) Qualitative and quantitative analysis was carried out on the factors affecting the ditch level during the diversion of the inclined coal seam open-pit mine, and the height of the ditch and the internal displacement of the ditch, the internal displacement, the discharge of some stripped objects caused by the ditch, and the diversion were deduced respectively. The formula for calculating the amount of secondary peeling after.
(2) Taking the minimum value of the total cost of stripping material transportation costs during the diversion to ditch retention and the total cost of secondary stripping costs after diversion as the objective function, the overall cost is constrained by restricting the height of ditch retention in different periods, and the level fluctuation of ditch retention is established. Mathematical model of the formula change. Taking an open-pit mine as an example, during the 7-year period when it turned to ditch retention, a set of most suitable ditch heights was output through fluctuating ditch retention, and the horizontal position of the side ditch retention in each of the next 7 years was obtained. Thus, the annual internal discharge volume, external discharge volume, and internal drainage ditch volume are further obtained. Through the comparison of the cumulative total cost, it can be concluded that compared with the traditional ditch at the same level, the total cost saved by this scheme is 148.3192 million.
Funding
This research was funded by the National Natural Science Foundation Key Project (U1361211) and National Natural Science Foundation General Program (51474119).
Author Contributions
Yu Wen: Data curation, Investigation, Methodology, Software, Validation, Visualization, Writing - original draft, Writing - review & editing
Ziling Song: Conceptualization, Formal Analysis, Funding acquisition, Project administration, Supervision, Writing - review & editing
Bo Zhao: Investigation, Resources
Mingjia Lv: Resources, Supervision
Data Availability Statement
The data used to support the findings of this study are available from the corresponding author upon request.
Conflicts of Interest
The authors declare no competing interests.
References
[1] Wang Zhaodong. Study on optimization of successive stripping engineering in mining areas of zoned open pit coal mines [D]. Liaoning University of Engineering and Technology, 2015.
[2] Bai Runcai, Bai Wenzheng, Liu Guangwei et al. Staging realm optimization of cross mining and internal discharge in narrow and long open pit mines with inclined coal seams [J]. Journal of Coal, 2017, 42(10): 2601-2608.
[3] Chang ZG, Chen YJ, Duan KP, et al. Study on the depth of triangular coal retention trench in parallel open-pit coal mines with internal drainage of pressure gang [J]. Coal Engineering, 2016, 48(03): 15-17.
[4] Liu GW, Li P, Li CS et al. Comprehensive optimization of drainage gang height and repeated stripping depth within adjacent mining areas in open pit mines [J]. Journal of Chongqing University, 2015, 38(06): 23-30.
[5] Zhang D, Luo Huaiting, Liu Y et al. Economic analysis of the height of the stay trench between mining areas of adjacent open pit coal mines [J]. Open pit mining technology, 2016, 31(06): 41-45.
[6] Liu P, Cai Q-X, Li J-B, et al. Optimization of pressure gang height between open pit mining areas based on marginal cost net present value method [J]. Chemical Minerals and Processing, 2017, 46(07): 25-28.
[7] Ma L, Xiao S. S., Chang Z. G. et al. Optimization of trench height between mining areas in open pit coal mines based on internal drainage of pressure gang [C]//Surface Mining Professional Committee of China Coal Society. Proceedings of the Eighth Scientific and Technical Symposium on Surface Mining. [publisher unknown], 2019: 10.
[8] Cheskidov V I, Reznik A V. Specifics of Internal Overburden Dumping in Open Pit Mining [J]. Journal of Mining Science, 2022, 58(2): 227-233.
[9] SONG Ziling, ZHAO Dongyang, ZHANG Yuhang, et al. Research on fuzzy evaluation of ecological environment evaluation system for green mining in open-pit coal mines [J]. Coal Science and Technology, 2019, 47(10): 58-66.
[10] Zhao Hongze. Research and Application of Key Technologies for Surface Mining of Near Horizontal to Tilted Coal Seams [D]. China University of Mining and Technology (Beijing), 2012.
[11] Chang ZG, Li KM, Chen YJ, et al. Study on the depth of right angle steering slow gang stay trench in open pit mining area [J]. Coal Engineering, 2014, 46(07): 88-90.
[12] Gryshova I, Shabatura T, Girdzijauskas S, et al. The Paradox of Value and Economic Bubbles: New Insights for Sustainable Economic Development [J]. Sustainability, 2019, 11(24): 6888.
[13] HUANG Fu. Long-term planning of internal dumping in surface coal mining [D]. Xuzhou: China University of Mining & Technology, 2017: 22-28.
[14] SONG Ziling, ZHAO Dongyang, ZHANG Yuhang. Optimization of green mining process system and process link matching model of open-pit coal mine [J]. Open-pit Coal Mining Technology, 2020, 35(05): 1-4.
[15] CAI Liping, LI Gang, SHI Wenzhong. Optimal design for land l expanding and conserving open pit dump [J]. Journal of China Coal Society, 2013, 38(12): 2208-2214.
[16] Xiao S. S., Huang F., Li K. M. et al. Long-term planning model of internal drainage in open pit mine and its solution method [J]. Journal of Coal, 2018, 43(04): 951-958.
[17] SONG Ziling, JIA Zhengzhao, WEN Yu. Blasting and crushing mechanism and optimization of blasting parameters in coal mine [J]. Journal of Liaoning Technical University (Natural Science Edition), 2024, 43(05): 556-564.
[18] Wen, Y., Song, Z., Fan, J. et al. Research on controlled mining of end slope fire-burned area in open-pit mine. Sci Rep 14, 21152 (2024).
[19] Wang Dong, Li Guanghe, Cao Lanzhu, et al. Layout method of soil discharge line in open-pit coal mine based on maximizing the utilization of internal discharge space [J]. Journal of China Coal Society, 2020, 45(09): 3150-3156.
[20] Song, Z., Wen, Y. & Jia, Z. Analysis of the impact of rock joint cracks on blastability of burnt rock in Xinjiang open pit coal mines. Sci Rep 15, 16179 (2025).
Cite This Article
  • APA Style

    Wen, Y., Song, Z., Zhao, B., Lv, M. (2025). Optimization of Retaining Ditch Height for Gentle Slope Turning in Inclined Coal Seam Open-pit Mines. International Journal of Energy and Environmental Science, 10(6), 162-173. https://doi.org/10.11648/j.ijees.20251006.14

    Copy | Download

    ACS Style

    Wen, Y.; Song, Z.; Zhao, B.; Lv, M. Optimization of Retaining Ditch Height for Gentle Slope Turning in Inclined Coal Seam Open-pit Mines. Int. J. Energy Environ. Sci. 2025, 10(6), 162-173. doi: 10.11648/j.ijees.20251006.14

    Copy | Download

    AMA Style

    Wen Y, Song Z, Zhao B, Lv M. Optimization of Retaining Ditch Height for Gentle Slope Turning in Inclined Coal Seam Open-pit Mines. Int J Energy Environ Sci. 2025;10(6):162-173. doi: 10.11648/j.ijees.20251006.14

    Copy | Download

  • @article{10.11648/j.ijees.20251006.14,
      author = {Yu Wen and Ziling Song and Bo Zhao and Mingjia Lv},
      title = {Optimization of Retaining Ditch Height for Gentle Slope Turning in Inclined Coal Seam Open-pit Mines},
      journal = {International Journal of Energy and Environmental Science},
      volume = {10},
      number = {6},
      pages = {162-173},
      doi = {10.11648/j.ijees.20251006.14},
      url = {https://doi.org/10.11648/j.ijees.20251006.14},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ijees.20251006.14},
      abstract = {Inclined coal-seam open-pit mines with internal dumping commonly reserve an end-side retaining ditch when turning from horizontal advance to along-strike excavation. Selecting a single fixed ditch level is straightforward but ignores year-to-year variability in stripping volumes and haulage distances, which can inflate the combined transportation and secondary stripping costs. This study proposes a two-stage optimization framework for planning the ditch-height trajectory during the turning period. First, a maximum economic ditch height is derived via an economic-compensation model that balances the revenue from overlying coal recoverable after turning against the added costs of longer haulage and increased external dumping, with cost/revenue streams discounted using a compound-interest formulation. Second, within this upper bound, a total-cost minimization model couples annual stripping transportation costs during turning with the secondary stripping cost after turning. The model enforces annual waste-volume balance among inner dumping, ditch storage, and external dumping, preferred waste-flow directions, bounds on ditch height, and limits on height differences between adjacent years. Haulage distances are calculated from centroid locations of stripping and dumping stages extracted from 3DMine, and the resulting dynamic program is solved using a sequential recursion method. A seven-year case study (2023-2029) outputs an optimized fluctuating ditch scheme with yearly ditch heights of 214.5, 190.5, 206.7, 201.3, 189.6, 181.2, and 166.0 m, reducing the cumulative cost by 148.32 million CNY compared with the conventional constant-level ditch plan. The framework offers a practical decision tool for parameterizing retaining ditches and improving the overall economics of gentle-slope turning in inclined coal-seam open-pit mines.},
     year = {2025}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Optimization of Retaining Ditch Height for Gentle Slope Turning in Inclined Coal Seam Open-pit Mines
    AU  - Yu Wen
    AU  - Ziling Song
    AU  - Bo Zhao
    AU  - Mingjia Lv
    Y1  - 2025/12/27
    PY  - 2025
    N1  - https://doi.org/10.11648/j.ijees.20251006.14
    DO  - 10.11648/j.ijees.20251006.14
    T2  - International Journal of Energy and Environmental Science
    JF  - International Journal of Energy and Environmental Science
    JO  - International Journal of Energy and Environmental Science
    SP  - 162
    EP  - 173
    PB  - Science Publishing Group
    SN  - 2578-9546
    UR  - https://doi.org/10.11648/j.ijees.20251006.14
    AB  - Inclined coal-seam open-pit mines with internal dumping commonly reserve an end-side retaining ditch when turning from horizontal advance to along-strike excavation. Selecting a single fixed ditch level is straightforward but ignores year-to-year variability in stripping volumes and haulage distances, which can inflate the combined transportation and secondary stripping costs. This study proposes a two-stage optimization framework for planning the ditch-height trajectory during the turning period. First, a maximum economic ditch height is derived via an economic-compensation model that balances the revenue from overlying coal recoverable after turning against the added costs of longer haulage and increased external dumping, with cost/revenue streams discounted using a compound-interest formulation. Second, within this upper bound, a total-cost minimization model couples annual stripping transportation costs during turning with the secondary stripping cost after turning. The model enforces annual waste-volume balance among inner dumping, ditch storage, and external dumping, preferred waste-flow directions, bounds on ditch height, and limits on height differences between adjacent years. Haulage distances are calculated from centroid locations of stripping and dumping stages extracted from 3DMine, and the resulting dynamic program is solved using a sequential recursion method. A seven-year case study (2023-2029) outputs an optimized fluctuating ditch scheme with yearly ditch heights of 214.5, 190.5, 206.7, 201.3, 189.6, 181.2, and 166.0 m, reducing the cumulative cost by 148.32 million CNY compared with the conventional constant-level ditch plan. The framework offers a practical decision tool for parameterizing retaining ditches and improving the overall economics of gentle-slope turning in inclined coal-seam open-pit mines.
    VL  - 10
    IS  - 6
    ER  - 

    Copy | Download

Author Information
  • College of Mining, Liaoning Technical University, Fuxin, China

  • College of Mining, Liaoning Technical University, Fuxin, China;College of Environmental Science and Engineering, Liaoning Technical University, Fuxin, China

  • Huaneng Yimin Coal Power Co., Ltd. Yimin Open-pit Mine, Hulunbuir, China

  • Shandong Gold Mining Co., Ltd. (Laizhou) Sanshan Island Gold Mine, Laizhou, China